Weather conditions and cameras at Mount Wilson
Quality Check SPICA (in progress)
2023
 May 1: Interesting engineering tests on E1-AO and different synthetic matrices. May 1: Interesting engineering tests on E1-AO and different synthetic matrices.
- May 2: Fog, rain and humidity. Lot of daytime activity on AO, alignment, dispersion, injection, spectral calibration
- May 3: Fog, humidity - no obs. Daytime activities on AO, alignment procedure, and issue probably found for the correction of dispersion.
- May 4: 100% humidity, Winter advisory, snow expected. No observations, continuation of daytime activities
- May 5: A few inches of snow during the day, fog and humidity. Continuation of daytime activities.
- May 6
- On April 6 & 7, CHARA is still closed after the winter break
 April 8: clouds for the first half of the time, then S1S2 fringes April 8: clouds for the first half of the time, then S1S2 fringes
 April 9: humidity for the first halp of the night then more fringes April 9: humidity for the first halp of the night then more fringes
 April 10: humidity for the first half of the night then alignment, AO, and more fringes April 10: humidity for the first half of the night then alignment, AO, and more fringes
2022
UT 1-5 December: Remote operations but no on-sky fringes because of poor weather
UT 4-8 November: Remote operations (Cyril, Sylvain, Fred, Nicolas, Denis + Julien)
Engineering activities on LDC/VLDC/DDL - Offsets on sky - Fringe tracking
 Log20221104.pdf
Log20221104.pdf  Log20221105.pdf
Log20221105.pdf  Log20221106.pdf
Log20221106.pdf
W2W1 fringes seen on the spicaRTD after stretching but still with some dispersion:  IMG_2724.MOV
IMG_2724.MOV
.
UT 4-11 October: onsite operations (Pierre, Julien, Denis)
More engineering activities on LDC/VLDC/DDL - Offsets on sky - AO & Fringe tracking - First set of initial data
 20221004.pdf
20221004.pdf  20221005.pdf
20221005.pdf  20221006.pdf
20221006.pdf   20221007.pdf
20221007.pdf   20221008.pdf
20221008.pdf   20221009.pdf
20221009.pdf   20221010.pdf
20221010.pdf   20221011.pdf
20221011.pdf
 S1S2 fringes on gam Cas as seen on the RTD (dispersion not completely compensated)  IMG_2691.MOV
IMG_2691.MOV
UT 12-19 August: Remote from Calern
Engineering activities on dispersion, baseline solution, and operations.
- August 19  log20220819.pdf log20220819.pdf
- August 18  log20220818.pdf log20220818.pdf
- August 17  log20220817.pdf log20220817.pdf
- August 16  Log20220816.pdf Log20220816.pdf
- August 15  Log20220815.pdf Log20220815.pdf 15thOfAugust2022.pdf 15thOfAugust2022.pdf
- August 14  Log20220814.pdf Log20220814.pdf
- August 13  Log20220813.pdf Log20220813.pdf
- August 12  Log20220812.pdf Log20220812.pdf
UT 8-12 July 2022: Remote from Calern
UT 21-25 June 2022: Mt Wilson (Denis, Fred, Julien)
- 25 June 2022: Commissioning, MLDC only
- Fringes S1S2 obtained on different stars, always the same offset (==> beam samplers different from STS)
- Fringes W1W2 on HD177724 at +3850µm on W1. Again a BS/STS issue.
- New TELAO telemetries under very good r0 conditions (18cm)
 
- 24 June 2022: Commissioning, but poor seeing
- New records of control and science data for tests of injection
- Hard time to find fringes because of a bad settings of the MLDC+VLDC
- New record of TELAO telemetries
 
- 23 June 2022: Array closed following the power outage
- 22 June 2022: High winds, thunderstorms
- 21 June 2022: Commissioning (first 2T fringes)
- S1S2 fringes found on Eta Uma, MR720 and LR - Important dispersion
- Recording of Control and Science data
- Recording of sequence of injection (control and science)
- Recording of HD148857 (binary with separation 1.3'') for field characterization
- TELAO telemetries recorded
- Control data recorded with different settings of LABAO focus on S1/B5
 
UT 27-31 May 2022: Nice&Calern (Sylvain, Cyril, Philippe, Fred, Denis)
- 31 May 2022: spica-vis software activities
- 30 May 2022: spica-vis software activities
- 29 May 2022: very poor seing conditions, no SPICA-FT close loop possible
- 28 May 2022: operation of SPICA-FT, GD and PD loops up to 4 telescopes
- 27 May 2022: clouds but promising tests of SPICA-FT control loops
UT 23-27 April 2022: Mt Wilson (David, Denis, Fred)
- 27 April 2022: clouds and poor seeing.
- 26 April 2022: medium conditions. Tests of injection
- 25 April 2022: good conditions. Validation of the FTT and fiberexplorer but still low ejection level. Tests of refraction.
- 24 April 2022: very bad seeing, tests of alignment procedures
- 23 April 2022: clouds and hgh humidity
UT 28 Mars to 31 March 2022: Calern (Denis, Fred, Philippe, Sylvain)
- 31 March 2022: poor seeing, high humidity. Continuation of software activities and SPICA-FT closed loop.
- 30 MArch 2022: high humidity, no observations
- 29 March 2022: bad weather, no observations
- 28 March 2022: bad weather, no observations
UT 10-12 March 2022: Mt Wilson (Cyril, Daniel, Denis, Julien, Philippe, Pierre)
- 12 March 2022: tests of AO tuning and fiber injection.
- 11 March 2022: poor seeing and winds, no observations
- 10 March 2022: (First stellar light) alignment on sky; very poor seeing. Issues for injection and fringes.
 
            